141 Willoughby

Report — Week 1 · Oct 5, 2026

Brooklyn, NY · 23-story mixed-use

Overall complete

58%

Budget spent

0%

Target TCO #1

Apr 2028

Open violations

—

01

Budget

Initial budget · DD Buyout / Lender Estimate · 7.24.26

$0 spent of $82,023,203 total hard cost budget.

Sitework
$0 / $1,356,000
Demolition
$0 / $977,200
Concrete
$0 / $221,041
Masonry
$0 / $495,460
Metals
$0 / $857,041
Millwork & Trim (Furnish Only)
$0 / $537,739
Thermal & Moisture Protection
$0 / $316,083
Doors & Windows
$0 / $8,533,648
Drywall & Carpentry
$0 / $8,822,270
Stone & Tile
$0 / $2,902,063
Flooring
$0 / $1,421,010
Paint
$0 / $1,512,200
Specialties
$0 / $3,641,733
Equipment
$0 / $2,310,200
Elevators
$0 / $1,110,000
Plumbing & Sprinkler
$0 / $6,711,300
HVAC
$0 / $13,490,570
Electric
$0 / $8,292,734
Lobby & Amenities
$0 / $5,094,150
Trade sub-total$68,602,441
General Conditions (10%)$6,860,244
Contingency (5%)$3,773,134
Builder's Fee (3.5%)$2,787,384
Total Hard Costs$82,023,203
02

Progress Photos

Mat foundation pour, cellar level

Mar 14, 2026

Mat foundation pour, cellar level

Framing & MEP rough-in, floor 4

Aug 22, 2026

Framing & MEP rough-in, floor 4

Brick facade and window install, north elevation

Sep 30, 2026

Brick facade and window install, north elevation

03

Construction Timeline

  1. Aug 2026

    100% CD documents

    Complete

  2. Sep 2026

    Ownership closing & mobilization

    Complete

  3. Oct 2026

    Phase 1 demo starts

    In progress

  4. Jan 2027

    Window installation begins

    In progress

  5. Apr 2028

    TCO #1 (floors 8–18)

    In progress

04

Project Schedule

Baseline schedule issued Sep 15, 2026 · 153 tasks

ALTCO ApprovalsDec 15, 25 – Jan 8, 27Active
Site Safety Plans / DOT LogisticsMar 10, 26 – Oct 19, 26Active
◆SSP / DOT Logistics - ApprovedOct 19, 26Upcoming
EARLY PACKAGESJun 1, 26 – Oct 19, 26Active
Temp Hoist / ShedSep 22, 26 – Oct 19, 26Active
Drywall & CarpentrySep 1, 26 – Oct 5, 26Active
Kitchen/ Vanity / Med CabSep 1, 26 – Oct 26, 26Active
Balance of Resi TradesAug 11, 26 – Dec 28, 26Active
Amenity FinishesNov 3, 26 – Jan 25, 27Upcoming
◆80% Buy Out - TargetNov 16, 26Upcoming
Window Shops & ApprovalsJul 28, 26 – Oct 19, 26Active
◆Target Glass DeliveryDec 8, 26Upcoming
◆Target Mullion DeliveryNov 23, 26Upcoming
New Windows - AssemblyDec 8, 26 – Mar 1, 27Upcoming
New Windows - FabricationSep 29, 26 – Mar 1, 27Active
Elevator Shops & ApprovalsSep 15, 26 – Oct 26, 26Active
Hollow Metal Shops & ApprovalsOct 27, 26 – Nov 23, 26Upcoming
Kitchen Shops & ApprovalsNov 24, 26 – Jan 4, 27Upcoming
MEPS Shops & ApprovalsSep 29, 26 – Jan 18, 27Active
MEPS CoordinationOct 13, 26 – Feb 15, 27Upcoming
Coordination - Cellar LevelOct 13, 26 – Nov 2, 26Upcoming
Coordination - LobbyOct 27, 26 – Nov 16, 26Upcoming
Coordination - Level 2Nov 17, 26 – Dec 7, 26Upcoming
Coordination - L8 & L9Dec 1, 26 – Dec 21, 26Upcoming
Coordination - L10 thru L14Dec 22, 26 – Jan 11, 27Upcoming
Phase 1 Demo - Soft / Slab OpeningsOct 27, 26 – Dec 28, 26Upcoming
Phase 2 Demo - Mech / RisersDec 29, 26 – Mar 1, 27Upcoming
Hoist & Bridge - Approval & InstallOct 20, 26 – Dec 14, 26Upcoming
Elevator - Low Rise ModernizationNov 24, 26 – Feb 1, 27Upcoming
Swingstage - Rig Set Up & Exterior Caulk RemovalsOct 20, 26 – Dec 28, 26Upcoming
Mechanical Rm - Riser Relocations / OffsetsOct 27, 26 – Dec 28, 26Upcoming
MEP - Shutoffs / CapsSep 29, 26 – Oct 26, 26Active
Mech - Re-tie & Start Up Commercial FloorsDec 29, 26 – Jan 25, 27Upcoming
05

Design Team

Architect

Studio North Architects

  • Facade details rev 4.pdfView
  • Lobby elevations.pdfView

Structural Engineer

Halvorsen Structural

  • Roof framing RFI 112.pdfView

MEP Engineer

Kessler MEP

  • Riser diagrams.pdfView
  • Mech roof layout.pdfView

Interior Design

Atelier Fenn

  • Unit finish schedule.xlsxView
06

Safety & Violations

Days without incident

47

Inspections this month

6

Workers on site today

38